PHASE/Tasks

Deliverable/

Documents Produced

Who

Assigned


Initial Due Date

Final Due Date

Percentage completed (%)

INCEPTION






Hold Initial Project Meeting

Minutes

Entire Team

09.30.09

09.30.09

100

Produce Minutes

Minutes

Adil Arif

09.30.09

12/02/09

100

Produce Project Plan

Project Plan

Adil Arif

10.25.09

10.27.09

100

Hold Initial Customer Interview

Notes

Entire Team

10.16.09

10.16.09

100

Create Website

Team Website

Patrick Yount

10.11.09

10.13.09

100







ELABORATION






Construct use case diagram

Use case diagram

Entire Team

10.13.09

12.10.09

100

Create initial list of functional requirements

Functional requirements

Robert Hall

10.20.09

12.10.09

100

Create Actor Descriptions

Actor Descriptions Document

Patrick Yount

10.20.09

12.10.09

100

Construct Class Diagrams

Class Diagram

Adil Arif, Geoff Montee

10.20.09

12.10.09

100

Generate Class Descriptions

Class Descriptions Document

Yao Yaun

10.27.09

12.10.09

100

SRS III

SRS II document

Robert Hall

10.20.09

12.10.09

100

SRS IV

SRS IV document

Robert Hall

10.20.09

12.10.09

100

Attribute Descriptions

Attribute Descriptions document

Yao Yaun

10.20.09

12.10.09

100

Raw Use Case Point Analysis

Raw Use Case Point document

Adil Arif

10.27.09

12.10.09

100

Screens and Reports List

Screen and Reports list documents

Robert Hall

10.27.09

12.10.09

100

Use Case Descriptions

Use Case Descriptions documents

Entire Team

11.03.09

12.10.09

100

Method Descriptions

Method Descriptions documents

Entire Team

11.10.09

12.10.09

100

Pert Chart

Pert Chart

Entire Team

11.03.09

12.10.09

100

Scenario Analysis Tables

Scenario Analysis Tables Document

Entire Team

11.10.09

12.10.09

100

Functional Test Cases

Functional Test Cases Document

Entire Team

11.17.09

12.10.09

100

User Navigation Matrix

User Navigation Matrix Document

Entire Team

11.24.09

12.10.09

100

HCI Prototype Presentation

HCI Prototype Presentation

Entire Team

11.17.09

12.10.09

100

SRS Presentation

SRS Presentation

Entire Team

11.30.09

12.10.09

100













CONSTRUCTION






……






TRANSITION















Member Name

Use Case

UCP value

# of Screens

# of Reports






Adil Arif

Create Comment, Edit Comment, Delete Comment, Report Inappropiate Comment, Delete Artifact, Create Sigla Tag

6

2

0

Patrick Yount

Upload Artifact, Update News

2

1

1

Yao Yaun

Login, Update Profile, Verify Researcher, Edit Researcher, Delete Researcher

5

3

0

Robert Hall

Edit Artifact, Search by Attribute, Search by Tag

3

3

0

Geoff Montee

Register as a Researcher, Administrate

2

2

0







TOTAL UCP

18

11

1